Zagreb, 23 November 2026 – INA has successfully completed drilling and completion operations on the new Ida C-4 DIR well in the northern Adriatic, which is currently delivering approximately 165,000 cubic metres of natural gas per day. Meanwhile, the new Irena-3 platform has been installed, with gas production scheduled to begin in the first quarter of 2027.

The latest success in INA’s northern Adriatic gas field development campaign is the Ida C-4 DIR well, which was drilled, completed and tied into the production system, with extended well testing commencing just 18 days after drilling operations were completed. Ida C-4 DIR is the third well in INA’s ongoing northern Adriatic drilling campaign, representing an investment of approximately EUR 65 million. Combined production from Ida C-4 DIR and the two previously completed wells, Ana-4 DIR and IKA JZ-6 DIR, amounts to approximately 340,000 cubic metres of gas per day, exceeding the initial production forecast for these wells by 21%.
The results of the campaign, together with contributions from other projects implemented during 2025 and 2026, including the Ika A wells, are reflected in INA’s overall Adriatic gas production. Daily output has risen from approximately 380,000 cubic metres before the campaign began in 2025 to the current level of 760,000 cubic metres. INA has thus doubled its daily Adriatic gas production, demonstrating its commitment to continued investment in domestic energy resources.
New Irena-3 platform installed
The next step in developing Adriatic gas production is the new Irena-3 production platform, recently installed as part of INA’s joint project with Energean. CROSCO’s Labin jack-up drilling rig has commenced wellbore construction at the location. The project also includes the installation of an eight-kilometre subsea tie-back pipeline connecting Irena-3 to the existing Izabela North platform. First gas is expected in the first quarter of 2027.
“The results we are achieving in the northern Adriatic confirm the importance of continued investment in domestic gas production. This production growth is primarily the result of well-planned and efficiently executed operations, the expertise of our employees and cooperation with our partners. We are particularly pleased that Ida C-4 DIR was tied into the production system so soon after drilling was completed and that its initial performance is exceeding expectations. At the same time, the installation of the Irena-3 platform marks an important step towards bringing additional Adriatic production capacity on stream. We continue to invest in strengthening domestic natural gas production over the long term, thereby contributing to Croatia’s security of supply,” said Josip Bubnić, Operating Director of Exploration and Production at INA.
Continued investment in onshore exploration
Alongside the development of Adriatic production, INA continues to invest in onshore exploration. In 2026, the company increased its interest in the SAVA-07 exploration block from 40% to 100% by acquiring Vermilion’s remaining interest. Four exploration wells were drilled during the first exploration phase, and the second phase is currently underway.
In addition, INA further expanded its domestic exploration portfolio this spring, securing exploration licences for two new blocks, SAVA-10/1 and DRAVA-02/02, through an international licensing round. Over the next three years, the company will carry out exploration activities to assess their hydrocarbon potential. Onshore seismic acquisition in the DRAVA 02/02 area began in late October.
Through investment in new wells, production infrastructure and exploration, INA continues to develop domestic oil and gas resources and contribute to Croatia’s security of supply.
About INA Group
INA Group plays a leading role in the Croatian oil business and holds a significant position in the region in oil and gas exploration and production, oil refining, and distribution of oil and petroleum products. The company consists of several subsidiaries wholly or partially owned by INA, d.d. The Group is headquartered in Zagreb, Croatia. In the field of oil and gas exploration and production, INA currently operates in Croatia and Egypt. Oil refining takes place at the Rijeka Refinery, while the Sisak industrial site is being transformed into a hub for sustainable alternative activities. The regional retail network includes more than 500 service stations in Croatia and neighbouring countries. INA Group is a member of the MOL Group.
PR contact
Avenija Većeslava Holjevca 10, Zagreb
Phone: +385 1 6450 552 | Email: pr@ina.hr